Lasting Impressions Price & Payments Update

This Update of the Price and Payments under the original contract agreement (1st October 2024) is made and entered into as of:
21st January 2025 by and between:
Client
Name: Mr Don Jordan & Mrs Agatha Jordan
Address: Limlair, Carriacou, Grenada, Westindies
Email: don@powerfulphotography.co.uk
Phone Number: +44 7970 287502
AND
Contractor
Business Name: Lasting Impressions
Director: Mr Laurie Lessey
Engineer & Project Manager: Mr Nathan Peter Lessey
Address: La Digue, St.Andrew, Grenada
Email: Nathanlessey473@gmail.com
Phone Number: +1 (473) 537-0306
The Owner and the Contractor may be referred to individually as a “Party” and collectively as the “Parties.”
This Construction Contract (the “Contract”) is made valid upon signature by all Parties.
The Parties agree as follows:

2. CONTRACT PRICE AND PAYMENTS

The Owner agrees to pay the Contractor the outstanding amount of EC$16266.43
plus an additional amount of EC$15000.00 for extra unforeseen works.
The final and total amount payable EC$31266.43 (the “Contract Price”).

Payment of this amount is subject to additions or deductions in accordance with any mutually agreed to changes and/or modifications in the work. Payment can be made by [cash/check/money order/credit or debit card/wire transfer/other]. Payment can also be made in installments upon completion of different milestones as agreed by both the Owner and the Contractor. The following schedule to be followed and checked by the contractors project manager and 3rd party agreed by the owner before making payments:

Payment on completion of stage six (6)
($6000.00)


Form work and casting of first floor ring beam and cladding of main roof with ply

Payment on completion of stage seven (7) ($2000.00)

Installation of 6" HCB wall under ridge board and at gable ends

Payment on completion of stage eight (8) ($2000.00)

Dowelling 1/2” bars at 16” O.C into existing beam inserting hurricane straps into existing ring beam Installation of 2"x 6" rafters for bedroom and veranda.

Payment on completion of stage nine (9) ($6558.35)

Plumbing required for installation of shower toilet and vanity and installation of shower vanity and toilet

Payment on completion of stage ten (10) ($2000.00)

Form work and casting of veranda ring beam

Payment on completion of the eleventh stage (11) ($10000.00)

Cladding of veranda roof and guttering

Payment on completion of stage twelve (12) ($7213.65)

Installation of Metal Galvanise and bat proofing of main roof & Veranda

Payment on completion of the 13th stage 10% ($5052.78)

Electrical work and complete cleaning of site to original condition and final inspection, once satisfied monies are to be released.

Owner Full Name
1st Owner
2nd Owner
Owner Address
Where works are to be carried out
1st Owner
2nd Owner
Lasting Impressions
Contractor Names
Lasting Impressions
Contractor Names
Lasting Impressions Address
Contractor
Director
Engineer - Project Manager
Independent Witness Name